Officials with the Town of Edson say the intersection of 18 Avenue and 48 Street will be closing once again on Monday, July 8, with the intersection of 18 Avenue and 49 Street re-opening to traffic.
Crews with Enterprises LTD say they have completed work on underground utilities in the area and are now moving on to reconstructing the road. Crews say they are in the process of placing down a gravel road, with concrete curbs, gutters and sidewalks being installed on July 15, and paving beginning on July 22, weather permitting.
Officials say affected residents along 18 Avenue will still be able to access their property from the back lane. All other traffic will be diverted to 49 Street and 12 Avenue as a detoured route.
Drivers are being asked to obey all signage posted in the area. Officials apologize for any inconvenience this work may cause and are thanking residents for their patience.