In the face of calls for multiple employee terminations and allegations of bias against renewable energy projects, the Alberta Utilities Commission (AUC) maintains that its denial of a solar farm project proposed near Whitecourt was due to the proponent’s insufficient application.
In February 2025, the Town of Whitecourt received a development permit application from Dutta Energy Corporation (DEC) for the Sunbeam Meadows Solar Project. The permit was approved with about 25 conditions, including an acknowledgement that AUC approval was still needed.
The DEC estimated that, considering the construction, operation and decommission phases of the project, between 270-405 jobs would have been introduced to the Whitecourt region, along with other economic benefits.
Jennine Loberg, director of planning and development for the town, said in addition to the economic benefits, the project would have used land with no current utilization without hindering future projects.
“The nice thing with a solar collector farm is it could run its course — I believe it’s a 20- to 30-year lifespan for these types of projects — and then still leave the land in a state where you can easily redevelop it after this use is complete,” she said.
That being said, Loberg acknowledged that multiple technical steps still needed to be taken by the DEC to flesh out its application. While the town was disappointed to see the project denied, it understands that the AUC has its own, more detailed requirements.
“They’re the technical experts when it comes to these things, so we understand that they have their process and requirements that need to be followed,” Loberg said. “The town relies on them to make sure it’s built properly to the current standards for these types of facilities.”
The project was denied by the AUC in February this year. Its report outlined a deficient application and concerns about conduct and compliance from the DEC if the project were to be approved.
Specifically, the commission found, “that information provided by the applicant is technically deficient, unreliable, and lacks credibility.”
According to the AUC’s decision, the proposed facility site is mostly intact forest and falls within a key wildlife biodiversity zone.

The proposed site for a solar farm development near Whitecourt. (Captured from AUC Decision 30003-D01-2026/Alberta Utilities Commission)
As mandated, the DEC completed field surveys to evaluate environmental impacts, but allegedly found no evidence of wildlife habitats or features. The AUC said, given the characteristics of the area, “properly conducted field work would be expected to result in some observation of wildlife, birds, dens or nests, evidence of sensitive habitats (e.g., wetlands), or indicators of suitable habitat for sensitive species.”
This misalignment raised concerns that environmental studies were not carried out adequately. The AUC also said the company’s plans for connecting the facility to Alberta’s power grid were either unclear or appeared to be designed to avoid regulatory scrutiny, rather than being grounded in sound engineering or planning.
The AUC also said the applicant resisted providing key details about the project, argued with the basis of the commission’s questions and disputed its authority over certain elements of the application process.
For example, according to the AUC, the DEC asserts that Alberta Environment and Protected Areas (AEPA) supported the proposed location due to “low impacts on wildlife,” and the AUC’s characterization of the environmental factors was erroneous. The DEC filed three motions about this concern, which were all addressed in an interlocutory ruling confirming that the AUC is considered an expert tribunal that can use its own expertise to come to a different conclusion than a body like AEPA.
The DEC raised multiple other concerns regarding the denial of this application with the AUC and the Alberta government.
It called for the termination of four AUC staff members connected to its application. The company alleged the employees demonstrated “repeated failures in competence, judgment, procedural
fairness, factual accuracy and administrative performance.”
More specifically, it referenced repeated non-compliance with timelines for producing records, “erroneous requests” for spring and fall bird migration surveys, mischaracterization of the site, its environmental record and DEC’s mitigation measures.
Beyond that, the company suggested the AUC “may be discouraging or delaying renewable energy development in Alberta.”
In response to the calls for termination, the commission commented, “The AUC staunchly rejects all of the comments that Dutta Energy Corporation has made against its employees. The employees in question are dedicated public servants and have the full support of the entire organization.”
The commission also asserted that its approval record proves it does not discourage renewable development: as of March 31, the AUC says four renewable projects have been approved in 2026; 20 were approved in 2025; and 29 were approved in 2024.
In response to the DEC’s concerns, the Ministry of Affordability and Utilities stated the AUC’s responsibility is to ensure projects meet high environmental and regulatory standards, and it does not weigh in on the commission’s decisions.
The AUC said the DEC has submitted an application requesting a review of this decision, which is currently underway.
“As a quasi-judicial tribunal, the AUC is unable to comment further while the matter is before the commission,” representatives said.











